Kwamoka Energy Ltd · Kumasi, Ghana

Sun and wood waste, one power plant.

We are developing a 16 MW hybrid solar and biomass power plant in Kumasi: 8 MW of solar PV, 8 MW from wood waste, 14 MW to the national grid.

Partner with usThe power project

Kwamoka Energy Ltd is the renewable energy company of the Kwamoka Group. We are developing the first and best of its class hybrid solar and biomass power generating solution in Ghana, at the Oti Light Industrial Area in Kumasi.

Our mission is to engage in the generation of sustainable, cost-effective energy through renewable resources, with emphasis on biomass and solar.

Licensed
Provisional licences from the Energy Commission to generate and supply energy from solar and biomass sources.

About us

Stream one

The sun. 8 MW of solar PV.

Phase one of the project is the development of an approximately 8 MW solar PV power plant, harnessing what the mission calls the sun's unlimited potential.

Phase one
8MWsolar PV
Source
SunGhana's daylight

The power project

Rows of solar panels in bright sun with trees on the horizon
The surface of a solar panel catching the sun
Heaps of sawdust and offcuts under an open shed at a wood-processing yard, late afternoon
A heap of wood chips, cocoa pod husks and rice husk

Stream two

Wood waste. 8 MW that would otherwise be burned for nothing.

The Sokoban Wood Village generates more than 150 tonnes of wood waste per day, excluding additional wood waste generated by larger wood-processing companies operating in the surrounding area. The project will utilise this available resource, together with agricultural residues, to generate clean and reliable electricity.

Sokoban Wood Village
150t/dayof wood waste today
Planned feed
265t/dayof bio-waste at the plant
  • Wood waste
  • Agricultural residues
  • Cocoa pod husks
  • Forest residue
  • Rice husk
A hybrid power plant at dusk: a biomass boiler hall with a tall stack, lights on, and a field of solar panels in front

One plant

Two streams. One 16 MW hybrid plant.

  • 8 MW of solar PV while the sun is up.
  • 8 MW of waste-to-energy from wood waste and agricultural residues.
  • 16 MW installed. 14 MW delivered to the national grid, 2 MW to run the plant.

How the project is built

Map sketch of the project site and its neighbours The project site at the Oti Light Industrial Area is about 2 km by road from the Sokoban Wood Village and about 2.5 km by road, or 400 metres in a straight line, from the ECG substation. The project site Oti Light Industrial Area Sokoban Wood Village 150+ tonnes of wood waste a day ECG substation 2 km by road 2.5 km by road 400 m as the crow flies
Sketch of the site and its neighbours, not to scale.

Delivery

14 MW to the national grid, from a substation 400 metres away.

The project is also strategically positioned close to an Electricity Company of Ghana (ECG) substation, located approximately 2.5 km by road, or about 400 metres aerial distance, from the project site. This proximity is expected to reduce the cost and complexity of connecting the project to the national grid.

The project site is located at the Oti Light Industrial Area in Kumasi, Ashanti Region, approximately 2 km by road from the Sokoban Wood Village. This strategic location provides direct access to a substantial and reliable supply of wood waste, which will form a major component of the feedstock for the waste-to-energy plant.

Steel gantries and transformers at a substation at golden hour

Where the project stands

Advanced, and positioned for financial close.

The project is at an advanced stage of development, with key milestones already achieved.

  1. Project land secured

    The site at the Oti Light Industrial Area, Kumasi.

  2. Power purchase agreement signed with ECG

    The Electricity Company of Ghana is the offtaker.

  3. Key permits and approvals obtained

    Including provisional licences from the Energy Commission for solar and biomass generation.

  4. Technical and environmental studies completed

  5. Project positioned for financial close

Our values

  • Protecting people and the environment

    A system of operation that conforms to environmental and technical standards.

  • Sustainability

    Meeting the needs of the present without compromising future generations.

  • Innovation

    Ideas that improve sustainability, productivity and efficiency.

  • Safety

    Fatal incidents are preventable, so injury prevention comes first.

  • Excellence

    World-class performance, and the drive to keep improving.

Our values in full

Join us in powering a cleaner and more sustainable future.

Kwamoka Energy welcomes strategic investors, development partners, technology providers, financiers and other stakeholders interested in supporting the development of this transformative renewable energy project.

  • Strategic investors
  • Development partners
  • Technology providers
  • Financiers

Partner with us

Single-line diagram of the hybrid plant Sun feeds an 8 MW solar PV generator and wood waste feeds an 8 MW waste-to-energy generator. Both connect to one 16 MW busbar, which delivers 14 MW to the national grid and 2 MW to the plant itself. The sun: 8 MW of solar PV Wood waste: 8 MW of waste-to-energy The plant: 16 MW installedGG The grid: 14 MW delivered Sun Wood waste 8 MW solar PV 8 MW biomass 16 MW 14 MW to grid 2 MW plant
The plant, as a single-line diagram.